Design and build of new office space for a leading investment management company

Client / 
Investment management company
Sector / 
Ufficio
Location / 
Luxembourg

Agilité was appointed to provide design and construction management of new office space in Luxembourg for a premier investment management specialist. 

Agilité Office

Commercial interior fit out for a new workplace for a premier investment management specialist, including reception area, meeting rooms, open plan spaces, server and patch rooms, and two kitchenettes.  

Agilité Project Investment Management company 2022
A P C E

PACE è il segreto del nostro successo, scopri come ci ha aiutato a raggiungere i nostri obiettivi di seguito

Pianificare

The project had a clear timeline of three months for pre-construction work and four months for construction, and a fixed budget. The design phase took longer than expected, due to additional requests, but the overall deadline was met through detailed planning. This included construction programming, programme advice, procurement, technical due diligence, and third-party and local authority liaison and permitting.  

Allineare

Agilité worked with the client’s architects during the design phase in order to manage any design conflict and provide value engineering – due to the fixed budget. During the construction stage, we had weekly reports with the client and the architect. Challenges, included materials with long-lead times, including partitions and bespoke joinery. These items were ordered as soon as we started on site, to avoid delays.  

Comunicare

To stay on schedule, we used Procore construction software for information requests, document management, submittals and communication between the different stakeholders involved in the process. Weekly meetings were held both on site and offline with the client and architects.

Eseguire

Delivery was on time, despite the design phase taking longer than expected, due to additional design requests. This meant the budget was slightly higher than originally set and cost planned. Environmental impact and cost were reduced by the client taking sustainable measures including reusing existing office furniture, and use of existing lighting and new LED lighting.  

The design and construction saw the creation of new office space incorporating a reception area, meeting rooms, open plan spaces, server and patch rooms and two kitchenettes. Long lead times for bespoke joinery and new requests meant flexibility was central to ensuring the project was completed on time, and to the standard expected.

FREDERICA PISACANE
JUNIOR PROJECT MANAGER

Casi studio

Esplora il nostro portafoglio di interni commerciali per saperne di più sui progetti di allestimento e ristrutturazione che abbiamo realizzato e sugli entusiasmanti marchi con cui abbiamo lavorato.

VISUALIZZA PROGETTI

careers@agilitesolutions.com
FR +33 (0) 1 88 61 81 31
UK+44 (0)7 506 403 069
IT +39 (0) 350 9646921
LUX +352 (0) 621 481 103

Certificazione n. 19535
Nota sulla Certificazione

Inviaci un messaggio per iniziare la conversazione.

"*" indica i campi obbligatori

Questo campo serve per la convalida e dovrebbe essere lasciato inalterato.
Contattaci